PMP Formula Reference
Every formula tested on the 2026 PMP exam.
Earned Value Management (EVM)
Most common. Assumes current CPI holds for remainder.
Assumes remaining work done at planned rate.
Use when a new estimate for remaining work is available.
How much more is needed to finish the project.
Performance required on remaining work to meet BAC. TCPI > 1 = harder than current rate.
Schedule & Network
N = number of stakeholders
Zero float = critical path activity
Amount activity can slip without affecting successor's ES
Used in network diagrams; some formulas use EF = ES + Duration
Backward pass calculation
Risk
Used for decision trees and contingency reserve calculation
Sum of all risk EMVs gives total exposure
Financial / Business Value
Higher ROI = better investment
r = discount rate, t = time period. Higher NPV = better project.
How long until investment is recovered. Lower = better.
BCR > 1.0 = project delivers value. Higher BCR = better.
The discount rate at which NPV = 0. Higher IRR = better project.
Quality (Statistics)
P = Pessimistic, O = Optimistic. Used in PERT.
O = Optimistic, M = Most Likely, P = Pessimistic
±3 sigma contains 99.73% of all values in a normal distribution
Abbreviation Quick Reference
| Abbr | Full Name | Definition |
|---|---|---|
| BAC | Budget at Completion | Total approved budget for the project |
| AC | Actual Cost | Real cost incurred for work performed |
| EV | Earned Value | Budgeted cost of work actually completed |
| PV | Planned Value | Budgeted cost of work scheduled to be done by now |
| EAC | Estimate at Completion | Expected total cost of the project at completion |
| ETC | Estimate to Complete | Expected cost to finish the remaining project work |
| VAC | Variance at Completion | Expected over/under budget at project end |
| TCPI | To-Complete Performance Index | Required CPI on remaining work to meet target |
| EMV | Expected Monetary Value | Probability × Impact; used for risk quantification |
| NPV | Net Present Value | Present value of future cash flows minus investment |
| IRR | Internal Rate of Return | Discount rate at which project NPV equals zero |
| PERT | Program Evaluation Review Technique | Weighted average estimate: (O + 4M + P) / 6 |